Matundura substation

Project Details

  • Client: Kenya Power Ltd
  • Location: Nyandarua South district, Central province
  • The project involves supply and installation of plant & equipment and civil works. 
  • The civil works involve; 
  • Construction of 256m long, 3m high stone wall, plastered internally with horizontal key on the outer surface, razor wire on top and 5m wide gate. 
  • Construction of a 5m by 7.6m control room with cable trenches inside. 
  • Construction of a guard house and a pit latrine 6m deep. 
  • Construction of 57 no plinths as per the engineers design and 600mm by 600mm cable trenches within the station. 
  • Construction of the substation roads, with paving blocks, 4 m wide. 
  • The project was a Design and Build project (Turnkey)
  •  